A Jana Jol project has started in Atyrau OR, in the framework of which reconstruction of intrafactory roads is performed.

NSS employee perform installation of border stones, concreting in crossing points of underground services. Also on the territory of the plant NSS has installed 16 stops, 180 road signs, strips for pedestrians and bicyclist appeared. 30 employees of NSS company and 25 peaces of special equipment were involved in Road -construction works.
Total area, subjected to reconstruction of road pavement is 57000m2 sq. metres.

The repair works are planned to be completed till the end of October 2019.